Page 1
background image
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
Form 6-K
REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO
RULE 13a-16 OR 15d-16 UNDER THE SECURITIES
EXCHANGE ACT OF 1934
For
15 December 2014
Harmony Gold Mining Company
Limited
Randfontein Office Park
Corner Main Reef Road and Ward Avenue
Randfontein, 1759
South Africa
(Address of principal executive offices)
(Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-
F or Form 40-F.)
Form 20-F X
Form 40-F
(Indicate by check mark whether the registrant by
furnishing the information contained in this form
is also thereby furnishing the information to the
Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.)
Yes
No X
background image
Harmony’s Golpu Project to proceed to feasibility
Low capital development cost and high grades maximise free cash flow
Staged development of the Golpu deposit with the first stage (‘Stage 1’) targeting the
upper higher grade portions of the ore body
Stage 1 comprises of two block caves. The first block cave operating at 3Mtpa and first
production forecast for 2020, followed by a deeper block cave operating at 6Mtpa in
steady state from 2024
Attractive return on investment, with an estimated Internal Rate of Return (IRR) of 17%
Lowest quartile cost for copper including capital (C3) at US$1.42/lb and the cash cost
for gold at approximately negative US$1 700/oz
Approximate life of Stage 1 is 27 years, with annual production peaking at 320 000
ounces of gold and 150 000 tonnes of copper in 2025
Substantially lower project capital, with maximum negative cash flow of US$785m to be
funded by Harmony
Johannesburg: Monday, 15 December 2014: Harmony Gold Mining Company Limited
(Harmony) is pleased to advise that the Harmony board has approved the updated
prefeasibility study (PFS) of the Golpu Project in Morobe Province, Papua New Guinea
(PNG) and has agreed to progress the project to feasibility study stage (FS).
This updated prefeasibility study covers the first stage of Golpu’s development. Stage 1 of
the Golpu development targets the upper higher value portion of the orebody. Work will
continue on optimising a second stage mine development (Stage 2), which will encompass
the rest of the ore reserves. Both the feasibility study for the first stage and the updated
prefeasibility study for the second stage of the project are scheduled to be completed by the
end of calendar year 2015.
The updated prefeasibility study entails low development capital cost, targets high grades to
maximise free cash flow generation and demonstrates the potential of this world class ore
body.
“The updated prefeasibility study supports our view that Golpu is a spectacular ore body with
a large copper component, affordable and mineable. Key objectives of the study have been
achieved by reducing the capital of the project, lowering operating costs and improving the
rate of return”, said Graham Briggs, chief executive officer (CEO) of Harmony.
Issued by Harmony Gold
Mining Company Limited
15 December 2014
For more details contact:
Marian van der Walt
Executive: Corporate and
Investor Relations
+27 (0) 82 888 1242 (mobile)
Henrika Ninham
Investor Relations Manager
+27 (0) 82 759 1775 (mobile)
Corporate Office:
Randfontein Office Park
P O Box 2
Randfontein
South Africa 1760
T
+27 (11) 411 2000
www.harmony.co.za
JSE:           HAR
NYSE:       HMY
ISIN No.:  ZAE000015228
Registration number:
1950/038232/06
background image
Harmony’s CEO notes that the development of the Golpu Project aligns with Harmony’s strategy of profitable, low-cost
operations: “The conclusion of the updated PFS is a major project milestone and has demonstrated the significant
potential of this world-class orebody, which contains mineral resources of 20 million ounces of gold and 9.4 million tonnes
of copper. Attributable annual production for Harmony is significant and averages at 500 000¹ gold equivalent ounces per
year in years 2024 to 2029. Stage 1 is expected to have a life of approximately 27 years”.
The Golpu project team, with the assistance of WorleyParsons as project consultant, have incorporated a total of 52 000
new drill core samples into the updated study - significantly improving the understanding of the geological framework.
This has redefined the boundaries of the high grade porphyry event in the upper part of the orebody, which will be mined
by block caving method. This enables a reduction in the size of the footprint of the block caves compared to the 2012
prefeasibility study significantly reducing capital requirements.
The Stage 1 project capital on a 100% basis is estimated at US$2.3bn, yielding an attractive return on investment with an
internal rate of return of 17%. The updated prefeasibility study recommends the development of twin exploration declines
to establish further geotechnical and geological data to support the feasibility study. A decision on the declines is
anticipated in the first half of 2015.
The two proposed block caves in Stage 1 are designed to access approximately 40% of the contained metal (gold and
copper) of the Golpu reserve. The approximately 60% remaining of the reserve would be extracted by a future deeper
block cave (Stage 2). The mining and processing infrastructure of Stage 1 would then be utilised to support development
of Stage 2.
Engagement with key stakeholders, including the PNG national government, the Morobe provincial government,
landowners and community representatives continues to ensure clear alignment on the project objectives.
Golpu has the potential to deliver significant benefits to local and regional communities and the broader economy of
Papua New Guinea, including local business opportunities, taxation and royalty revenues to all levels of government. It
will also offer benefits through training and employment opportunities, business and community development
programmes, health and education investments and improved regional infrastructure.
Environmental baseline studies and risk and impact assessments were undertaken as part of the updated pre-feasibility
study and will be further developed during the feasibility study in preparation for the submission of an Environmental and
Social Impact Assessment to the PNG Government for consideration.
Harmony and Newcrest each own 50% of the Golpu Project through the Wafi-Golpu Joint Venture (WGJV). The PNG
government retains the right to acquire up to a 30% interest in the project, at any time up to the date of granting the
mining lease, at a price equal to the sunk costs at the date of acquisition. If this right is exercised, the government
becomes a full equity partner in the project .
“The Golpu project is a significant value accretive game-changer for Harmony”, says Graham Briggs, CEO of Harmony.
“Harmony intends to fund the earlier stages of the project from internal cash flows, and reviewing other funding options for
the latter stages. In the current environment of volatile gold prices, we are focussed - more than ever - on cost control and
cash generation at existing operations. In addition, shareholder value is created through investing in Golpu, securing a
sustainable, profitable future for Harmony.”
background image
Key items for Stage 1 (100%)
Area
Measure
Unit
Production
First ore
Date
2020
Steady-state production
Date
2024
Ore mined
Mt
146
Life of Stage 1
Years
27
Cu metal produced
Mt Cu
2.2
Au metal produced
Moz Au
3.7
Peak gold production (Year 2025)
koz pa
320
Peak copper production (Year 2025)
kt pa
150
Gold recoveries
%
77
Copper recoveries
%
94
Capital
Project capital
US$bn
2.3
Sustaining capital
US$bn
0.8
Total life of Stage 1 capital
Maximum negative cash flow
US$bn
US$bn
3.1
1.6
Operating
Total operating cost (real)
Cash cost (C1) (after gold credits)
Total production cost* (after gold credits)
Cash costs (after copper credits)
Total production cost* (after copper credits)
US$/t
US$/lb Cu
US$/lb Cu
US$/oz Au
US$/oz Au
34.6
0.78
1.42
~ negative 1 700
~ negative 950
Economic
assumptions
Gold price
US$/oz
1 250
Copper price
US$/lb
3.10
Exchange rates
AU$/US$
0.90
PGK/US$
2.58
Stage 1 outcomes
Percentage of reserve utilised
%
~40
Internal Rate of Return
Net present value (at a discount rate of 8.58%)
%
US$bn
17
1.1
*Includes capital
Overview of mining operations
Golpu is expected to comprise of at least two stages.
The updated prefeasibility study for Stage 1 of Golpu recommends two block caves accessing the high value core of the
Golpu ore body. Stage 1 extracts 146Mt at an average grade of 1.02g/t gold and 1.60% copper. The proposed start-up
production rate is 3Mtpa mined from Block Cave 1 (BC1) and 6Mtpa mined from the deeper Block Cave 2 (BC2).
BC1 is situated approximately 425m below surface and will extract 12Mt of cave ore over a five year period at a peak
production rate of 3Mtpa. During caving operations, ore from the block cave draw points will be delivered by diesel load
haul dump units to an underground jaw crusher and then conveyed to surface.
BC2 is situated approximately 1 050m below surface. BC2 will be mined at a rate of 6Mtpa to extract 134Mt of cave ore
over a 23 year period.
background image
Access to the orebody is planned to be via twin declines developed from the Watut River flats. During the production
phase it is envisaged that an inclined conveyor is installed in one of the declines for transportation of production ore to the
process plant located near the portal; the other being used for ventilation.
Schematic of proposed operations
The two proposed block caves in Stage 1 are designed to access approximately 30% of the tonnes, which contain
approximately 40% of the metal (gold and copper) of the Golpu reserve. The mining and processing infrastructure would
then be utilised to exploit the remaining 70% of the tonnes, which contain about 60% of the contained metal (gold and
copper) of the Golpu reserve. Stage 2 will focus on block cave 3 (BC3). Study work completed to date on Stage 1 and
Stage 2 combined indicates no material difference in metal recovered from the 2012 reserve.
Schematic cross section of Golpu porphyry deposit 2012 compared to 2014
background image
Capital costs and funding
The capital cost estimate has been completed to a Prefeasibility level of accuracy and includes all capital from 1 January
2015.
Stage 1 capital cost estimate (100%)
Area
US$m
Direct costs
Mine
893
Process plant
155
Infrastructure
554
Total direct costs
1602
Indirect costs
Project management
284
Owners' costs
127
Total indirect costs
411
Contingency
287
Total capital costs
2 300
Harmony’s 50% share of study and capital requirements for Stage 1 is estimated to be as set out in the table below.
Harmony equity
(50%)
Harmony equity (35%)
PNG Government
buy-in
Year
Project capital
US$m
Project capital
US$m
2HFY15
(15)
(15)
FY16
(55)
(55)
FY17
(105)
45*
FY18
(205)
(140)
FY19
(250)
(175)
FY20
(155)
(110)
Total
(785)
(450)
*Assuming PNG government buys a 30% interest in the project
Harmony will fund the first three years from operating cash flows and from FY18 onwards, debt financing will also be
considered. From FY21 Stage 1 will be cash flow positive after capital expenditure.
background image
Operating costs
The key driver for the mining costs is the power requirements for ventilation, cooling and mine dewatering, which
accounts for $6.56/t (55%) of the mining costs. The key driver for ore treatment costs is also power, which accounts for
42% of treatment costs.
Power is a key project driver that influences both mining and treatment cost assumptions. The study has used a power
price assumption of US20c/kWh. The Project will source bulk power from either its own power station or from an
independent power producer.
Operating costs
US$/t
Underground mining
11.83
Treatment
12.86
Infrastructure
3.17
General and administration costs
6.78
Total
34.64
Production profile of Stage 1
The Stage 1 production schedule below outlines the ore mined and the metal recovered from BC1 and BC2 (on a 100%
basis).
The cash flow for Stage 1 forecasts a maximum negative cash position of US$1.6bn in 2020 as the project moves into
initial production from BC1. Once BC2 is in full production in 2024, it is estimated the project will produce significant free
cash flows, with total undiscounted free cash flow of approximately US$5.8bn over the 27 year life of Stage 1.
Stage 1 positions Golpu as a lowest quartile cost producer with copper including capital (C3) at US$1.42/lb and the cash
cost for gold at approximately negative US$1 700/oz.
background image
Process plant, infrastructure and waste management
The updated study anticipates the construction of a 6Mtpa process plant scheduled for commissioning in the first year of
production in calendar year 2020, which will produce a copper-gold concentrate.
The Golpu project is located in a greenfields location. The main infrastructure requirements for the Golpu project are
access roads, tailings storage, water management, port facilities and power supply and transmission.
It is expected that the copper-gold concentrate will be filtered at the mine site and transported to the Port of Lae by trucks
for the initial production, with the concentrate to be pumped to the filtration plant located at the port as production rates
increase.
Summary of next steps
The updated prefeasibility study recommends the development of twin exploration declines to establish further
geotechnical and geological data. A decision on the declines is anticipated in the first half of 2015.
The feasibility study will address and finalise technical issues identified in the prefeasibility study. It will progress further
environmental, social and cultural heritage studies associated with access roads and tailings storage. Further work will
also be conducted to identify the optimal solution for power for the operations.
Advanced exploration activities are subject to board and government regulatory approval. The Harmony board will
consider the advanced exploration activity in the first half of calendar year 2015, once a pre-development agreement has
been concluded.
Both the Stage 1 feasibility study and the updated prefeasibility study for Stage 2 are targeted to be completed by the end
of calendar year 2015.
¹ Equivalent gold ounces converted by using a copper price of US$3.10/lb and a gold price of US$1250/oz
Please also refer to www.harmony.co.za/investors for the presentation in support of this release.
Forward looking statements
This release contains "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended, and
21E of the Securities Exchange Act of 1934, as amended, that are intended to be covered by the safe harbour created by such
sections. These statements may be identified by words such as “expects”, “looks forward to”, “anticipates”, “intends”, “believes”,
“seeks”, “estimates”, “will”, “project” or words of similar meaning. All statements other than those of historical facts included in this
release are forward-looking statements, including, without limitation, (i) estimates of future earnings, and the sensitivity of earnings to
the gold and other metals prices; (ii) estimates of future gold and other metals production and sales, (iii) estimates of future cash costs;(
iv) estimates of future cash flows, and the sensitivity of cash flows to the gold and other metals prices; (v) statements regarding future
debt repayments; (vi) estimates of future capital expenditures; and (vii) estimates of reserves, and statements regarding future
exploration results and the replacement of reserves. Where the Company expresses or implies an expectation or belief as to future
events or results, such expectation or belief is expressed in good faith and believed to have a reasonable basis. However, forward-
looking statements are subject to risks, uncertainties and other factors, which could cause actual results to differ materially from future
background image
results expressed, projected or implied by such forward-looking statements. Such risks include, but are not limited to, gold and other
metals price volatility, currency fluctuations, increased production costs and variances in ore grade or recovery rates from those
assumed in mining plans, project cost overruns, as well as political, economic and operational risks in the countries in which we
operate and governmental regulation and judicial outcomes. For a more detailed discussion of such risks and other factors (such as
availability of credit or other sources of financing), see the Company's latest Annual Report on Form 20-F for the year ended June 30,
2014 which is on file with the Securities and Exchange Commission, as well as the Company's other SEC filings. The Company does
not undertake any obligation to release publicly any revisions to any "forward-looking statement" to reflect events or circumstances
after the date of this presentation, or to reflect the occurrence of unanticipated events, except as may be required under applicable
securities laws.
Competent Persons Statement
The information in this presentation that relates to Exploration Results, Mineral Resources and Ore Reserves is based on information
compiled by Gregory Job, BSc, MSc, who has 26 years’ relevant experience and is a member of the Australian Institute of Mining and
Metallurgy (AusIMM) and a full-time employee of Harmony. He is entitled to participate in Harmony’s equity long term incentive plan,
details of which are included in Harmony’s 2014 Remuneration Report. Mr Job has sufficient experience which is relevant to the styles
of mineralisation and types of deposits under consideration and to the activity which he is undertaking to qualify as a Competent
Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves (the “JORC Code”). Mr Job consents to the inclusion in this presentation of the matters based on this information in the form
and context in which it appears. For details of Exploration Results, Mineral Resources and Ore Reserves refer to the Harmony
website.
ends.
background image
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused
this report to be signed on its behalf by the undersigned, thereunto duly authorized.
Dated: December 15, 2014
Harmony Gold Mining Company Limited
By:
/s/ Frank Abbott
Name: Frank Abbott
Title: Financial Director